Project information

  • Category: Road, Bridge & Transport Infrastructure
  • Client: Rural Access Programme-3; DFID-UK assistance
  • Project Start Date: January, 2014
  • Project End Date: August, 2017
  • Scope of Services: Stage 2 Survey & Design and Construction Supervision for implementation of Sanighat-Phukot-Syuna-Shipkhana (17.640 Km), Jarkot-Ramnakot (5.930 Km) in Kalikot District under RAP-3 DFID/UK assistance

Project Description

Rural Access Programme provided access to goods and services to poor households including creation of local employment through construction of environment friendly district roads adopting labour based methods, plus many support income generating activities for enhancement of livelihoods of project affected households. Besides labour-based methods, small equipment were also introduced in RAP-3.

In Kalikot, New Road Construction Supervision and Stage 2 Survey and Design in Kalikot District for implementation of Sanighat-Phukot-Syuna-Shipkhana (17.640 Km), Jarkot-Ramnakot (5.930 Km) total length 23.5 kilometers was taken up from RAP assistance.

Services

  • Review of the road alignment and stage one survey.
  • Stage 2 survey, detailed engineering design, engineering drawing and cost estimate of the road.
  • Carried out construction field survey works and alignment lay-out including verification of the cadastral survey.
  • Review the detailed design of the alignment adopting labor based participatory and environment friendly approach including preparation of site-specific structural design of longitudinal and cross drainage structures and retaining walls.
  • Preparation of detailed cost of construction contract packages for completion of road.
  • Preparation of site-specific EMP, carrying out environmental management and bio-engineering works.
  • Conduct technical training to construction supervisors, worker groups and road construction and maintenance committees.
  • Full-time construction supervision of the road including quality control.
  • Work evaluation preparation/certification of payment bills.
  • Organized approach orientation and road supervisor & RBG training.
  • Coordination with the local institutions like VDC, DDC, DRCC, UC/UG, Local NGOs, line agencies etc.
  • Preparation of Monthly Work Progress Reports, Annual Reports and Project Completion Report including As-Built Drawings